News

Project gets underway!

25 August 2025

The traffic islands and roundabout at the intersection of Haven Road and St Vincent Street have been removed.

These were removed to allow for the lane shift to block off the top end of St Vincent Street.

Over the next fortnight we will be upgrading the Haven Road wastewater pipeline at depths of approximately 3.5 to 4.0 meters.

It is a 40-year-old, 150mm diameter cement pipeline. We’ll be cutting and removing the existing road surface, then safely supporting the deep trenches while we dig. We’ll also put in a temporary section through the existing culvert, so it can later be lowered underneath the new twin pipes in the next stage of work.

Read more about how we safely support the deep trenches here.

Drone shot showing the road closed and work site