Stage Three underway

19 January 2026

Stage Three began on Monday 5 January and is well under way. During this stage of the project, expected to continue through till August 2026, our infrastructure upgrade works will continue south along St Vincent Street.

Work between January and March 2026:

  • 40m long wastewater pipeline at 3.8m deep
  • Removal of the existing pipeline and manhole
  • Re-align an 11kv cable and protect power ducts
  • Install a wastewater pipe underneath the existing stormwater box culvert
  • Construct a temporary stormwater gate to bypass stormwater around the worksite
  • Construct temporary works to support the existing box culvert and excavation.
  • Demolish the cover slab, roof and wall of the box culvert.
  • Install the next 35m of the twin 1800stormwater pipes.
Drone shot of the road closure