Grampians slip repairs nearing completion

15 September 2025

The retaining wall work on the Tawa Track is now complete, and track closures due to the project works are now reopened.

The Kahikatea Track and Ponga Track remain closed due to recent slips. Planting and maintenance work in these areas is ongoing, which may cause intermittent closures.

Upcoming work: Slips 27 & 47, are minor works higher on the Tawa Track, scheduled for summer 2025/26.

Post-construction remediation of the access track from Van Diemen St is planned, worked in around scheduling of slip remediation projects.

Slip updates on Grampians
map showing current closures of both paths