Project updates

During the August 2022 weather events, multiple slips occurred on the Grampians Reserve. These slips had an impact on both the reserve and private properties.

Work is about to start to remediate these slips, to reduce the chance of negative impacts occurring from future weather events.

Traffic management will be in place in some areas for construction vehicle access.

The remediation work will occur on the below slips:

  • Slip 14 – Tukuka Street (underway - planned completion late August) - Access available outside of work hours and weekends
  • Slip 12 – Allan Street (underway - planned completion late September)
  • Slip 18 – Collingwood Street (underway - planned completion November)
  • Slip 12 – Ronaki Track above Ronaki Terrace (Started September 2024)
  • Slip 16 – Tawa Track above Endeavour Street (Started September 2024)
Grampians Slips