April - May update

8 May 2020

With the shift to Alert Level 3, work has started again on the Saxton Creek project.

Last week the site got back up and running, with contractors and staff taking extra precautions as required. All the equipment was back on site and earthworks started again. Contractors also setup pumps in the next section of the creek and carefully removed the fish from this section.

This week, work really got underway. Excavation of the creek continued, to improve the path of the water (to help prevent flooding and erosion in the future). Rock was put in place, and the site was also protected against the rain we had.

The site was also surveyed for the kerb alignment, drainage and bridge deck.