Now you have seen what is proposed and what we are asking, here is what each stage would cost, and how it could be paid for.

The short version

Stages 1 to 3 together come to about $27.3 million, excluding GST and including a 40% allowance for cost rises. The Masterplan expects that work to happen over the next 10 to 30 years, as funding, partnerships, approvals and dependencies are resolved – not all at once.

These are early numbers

A cost expert – a quantity surveyor – worked them out in 2026, before any design work. Every number already includes an extra 40% in case costs rise, because it is still early days. GST is not included.

No money is committed

The Council has not set aside money to build any of this. Each stage would need its own decision through the Long Term Plan – the ten-year budget the Council consults the public on.

Some things are not counted

Buying land, taking down the old Four Seasons building, looking after existing structures, and day-to-day running costs are not in these numbers.

What each stage could cost
StageWhat it coversEarly estimate
Stage 1: Connectivity – joining it all upThe path, plus repairs and earthquake strengthening at the Anchor Building$3.0m
Stage 1: Connectivity – joining it all upThe path around the NCC Electricity Building, a wider Friendship Boardwalk, and decommissioning the old wharf$4.5m
Stage 1 total$7.5m
Stage 2: Activation – bringing it to lifeReshaped carparks and landscaping along the waterfront, with new bus stops$3.5m
Stage 3: Coordinated development – the big buildsThe NCC Electricity Building brought back into use, including the former wharf, the mural and the substation$12.0m
Stage 3: Coordinated development – the big buildsSteps into the sea, and a renewed boat ramp$4.3m
Stage 3 total$16.3m
Stages 1–3The work this plan proposes putting into the Long Term Plan$27.3m

Stage 4 – ideas for later

These need more work with others, or a change of ownership or use, before they could happen. None of them is up for funding yet.

Stage 4 – ideas for later
IdeaWhat it coversEarly estimate
Custom HouseFour options, from keeping it watertight through to removing it$0.25m – $5.5m
More steps into the seaA bigger swimming area with steps and an accessible platform$6.8m – $8.6m
Shed 1Extending the waterfront to Shed 1, working with Port NelsonNot yet costed
Yacht Club and SH6A wider path at the Yacht Club, and a new crossing over SH6Not yet costed

Source: quantity surveyor estimate assessment, Draft Haven Waterfront Masterplan, September 2026. All numbers leave out GST, are at 2026 values, and include a 40% allowance for cost rises.

Funding the Masterplan

No single pot of money covers this. Each stage would need a funding decision through a future Long Term Plan. Outside funding and private investment could also play a part.

For the old buildings, the Council could ask the market – inviting private partners to help pay for and run them, rather than paying for it alone. What comes back would shape what is realistic. No decision has been made on this either.

Should we look for money from outside the Council?

The Council could apply for grants and funding from central government, trusts and other funders, and could invite private partners to help pay for parts of the work. That would take pressure off rates.

But it comes with a catch, and we want to be straight with you about it: if we go looking for outside funding and do not get it, some of this work may not happen, or may be delayed.

Question 9, part two

Should we look for money beyond rates – knowing that if we do not get it, some of this work may not happen?

What this means for your rates

Agreeing a masterplan does not add anything to your rates. If a stage goes ahead, its cost – and what that means for rates – would be worked out and consulted on through the Long Term Plan, once the numbers are firmer.