Bridge to Better road closure

27 February 2026

​March road closure

From Monday 2 March work moves onto Bridge Street. This will require a closure between Rutherford Street and Collingwood Street. This is in addition to the current closures on Wakatu Lane and Haven Road.

This stage of the project will focus on the pipe upgrade on Bridge Street (West) and the historic brick lined sewer, built in the early 1870s. Rather than removing or replacing it, we’ll be preserving it by installing a liner inside the pipe protecting the original brickwork for the future.

Pedestrian access will be maintained while the road is closed.

Dates: 2 March – 29 March