Pump station project well underway

14 October 2021

It's been a hive of activity down around Awatea Place, with the pump station work well underway.

Awatea Place has been closed and residents have been provided with a temporary secured car park.

A temporary bypass pipe has also been installed to divert sewage away from the worksite, and work has started on the sheet piling for the storage tank foundations. Sheet piling is when they drive large metal beams into the ground so that they can dig down without the ground collapsing in.