Moving up the street and closing Pioneer Crescent

16 February 2023

The project has been progressing well during January, and the next stage of work is fast approaching. This will include the following:

  • Installation of the 1.8m diameter Stormwater pipeline to the end point.
  • Installation of a new manhole and 0.6m diameter Stormwater connection to Pioneer Cr.
  • Removal of contaminated coal tar material from the trench.
  • Removal of the redundant sewer pipeline.
  • Reinstatement of the kerb and channel.
  • Reinstatement of the road and footpath.

Key Information

The site will extend into Pioneer Crescent on Monday 13 February 2023 (area highlighted by the RED dotted line above).

The site will reduce in length on Friday 17 February 2023 (shown as ORANGE in the above map) and remain like this until the road and footpath have been completed in this area. We expect this to be in late March.

Access to Pioneer Crescent will be restricted to pedestrians only from Monday 13 February. This access is shown in BLUE in the above map. The road will be closed at the Hastings Street / Washington Road intersection.

Please can you make sure all vehicles are parked beyond the construction site by this date. The temporary carpark is available and we recommend you use this while the work is underway.

Access to Hastings St will be via St Vincent Street. Please note that rubbish and recycling are to be brought to the kerb as normal. The contractor will make sure that it is collected from there.

If you have any questions, please contact Anthony at the below number/email.

Tasman Civil Ltd - Contract Manager:

Anthony Jordan (mobile 022 618 7702)

anthony.jordan@tasmancivil.co.nz