Work is scheduled to begin in March 2025 on a 4-5 metre wide pathway adjacent to the Nelson Marina. This promenade will provide a safe space for all users, including cyclists, walkers, mobility scooters users or wheelchair users.

This project is part of the wider Marina Masterplan.

When the construction is complete, the area will be landscaped, with lighting a key element to make sure it is safe and visible.

Works in the Southern Zone (along Akersten Street) will begin first and the Central Zone (Ruby’s Café to Jetty F) is due for construction thereafter.

This project is being funded by the Ministry of Business, Innovation and Employment through a $1.13m grant and by Nelson Marina.

Arising from the Marina Masterplan, the promenade will be a 5 metre wide pathway, providing a safe space for all users, be it by bike, walking, pushchairs, mobility scooters or wheelchairs.

Following the construction, the area will be landscaped, with lighting a key element to make sure it is safe and visible.

The project will be split into two stages, a Southern Zone and a Central Zone. This will minimise the disruption to users and businesses in the area.

Southern Zone

Akersten Street will be reduced to one lane, controlled by traffic lights. This will mean pedestrians and cyclists will still have safe access to the Marina while work occurs.