Road closures on Haven Road

1 October 2021

When work gets underway we will need to close the road to make sure the work can get done safely. The following is a list of work and approximate times when they will occur.

  • 18/10/21 to mid/end of November. Working in the centre island of Haven Road between QE2 Roundabout and Vickerman Street. This will see minor lane shifts and speeds reducing to 30km
  • Mid/end of November to mid-December. Working at the QE2 Roundabout at Saltwater Creek. Work will occur mostly off the road. The left turning lane from QE2 drive into Haven Road will not be in place from 9 am to 3 pm
  • 10/01/22 to mid-February 2022. Road crossings of QE2 Drive and Haven Road. A diversion will be in place for this time. After this date, all work on Haven Road should be complete.
  • Mid-February to mid-March 2022. Work on Vickerman Street.
  • Please note - we are aiming to have no traffic management in place over the Christmas break, long weekends (Labour, Waitangi, Nelson anniversary).