Projects drawing to a close

21 March 2022

The stormwater work on Haven Road is now complete (towards Saltwater Creek). There are no more detours along this section of road.

The stormwater work will continue on Vickerman Street. This work is scheduled to be completed in May 2022.

The sewer project near Russell Street will be completed on Wednesday this week (23 March 2022).

The final reseal by Waka Kotahi will be completed in April/May 2022.

A big thank you to all the businesses, residents, and users along Haven Road. This project has been disruptive, but we now have new sewer and stormwater pipes in place that will meet the needs of the area for many years to come.